In Dubai, developers are required to place funds for the project in an escrow account regulated by the Dubai Land Department (DLD).
These funds can only be used for the construction of the project, providing protection for investors. Additionally, developers must meet specific progress milestones and obtain DLD approvals, ensuring transparency and accountability throughout the construction process.
What protects your money
If the buyer stops paying: what the developer may keep
| Construction done | What the developer may do |
|---|---|
| Over 80% | Keep the contract and claim the balance, ask DLD to sell the unit at auction, or cancel and keep up to 40% of the price |
| 60–80% | Cancel and keep up to 40% of the price |
| Under 60%, works started | Cancel and keep up to 25% of the price |
| Not started, not the developer's fault | Cancel and keep up to 30% of what was paid, refund the rest within 60 days |
First DLD gives the buyer 30 days' notice to pay. The buyer can still go to court.
Figures to know
Terms in this answer
- Escrow account
- A bank account for one project. Buyers' instalments go there, and the developer receives the money stage by stage as construction is confirmed. It protects buyers if the project stops.
- Dubai Land Department (DLD)
- The government body that registers property in Dubai. When a purchase is registered, the buyer pays a 4% fee plus an admin charge; off-plan purchases are registered too.
Sources
- Dubai Law No. 8 of 2007 on escrow accountschecked Nov 13, 2026
- Dubai Law No. 19 of 2017 amending Law No. 13 of 2008 (Interim Register)checked Nov 13, 2026
- Dubai Land Department: register the initial sale (Oqood)checked Nov 13, 2026
- Bayut: Dubai off-plan market report 2025 (DLD data)checked Nov 13, 2026
- The National: Central Bank mortgage cap ruleschecked Nov 13, 2026