Snagging · after handover

Defects after handover in Dubai

Moving in does not end the developer’s liability. Under Dubai Law No. 6 of 2019, art. 40, the developer repairs defective installations for 1 year from the handover of your unit and structural defects for 10 years from the completion certificate.

What the developer is liable for, and how long

Two periods, set by Dubai Law No. 6 of 2019 for jointly owned property: buildings and communities with common parts.

1 yearfrom the handover of the unit to you

Installations: mechanical and electrical works, sanitary and sewerage. If the owner does not take possession, the year runs from the completion certificate.

10 yearsfrom the completion certificate of the project

Structural parts of the building: defects the developer must remedy or rectify.

Your sale agreement may give you more, for finishes or for a longer period: the law keeps any other rights an owner has. Read the defects clause of your agreement.

How to claim a defect

In writing, with proof, while the period runs. Four steps.

Open the checklist
  1. 01Make the list

    Room by room, with a photo and the location of each defect; the checklist helps.

  2. 02Send it in writing

    To the developer’s customer care or handover team, by email, and keep the reference number.

  3. 03Agree dates

    Ask for a date for the repairs and be there, or leave access with someone you trust.

  4. 04Check the result

    Go through every item after the repairs and send back what is still open, under the same number.

If the developer does not answer

Dubai Law No. 6 of 2019 names who deals with it.

Common parts

A leak from the roof, a broken lift, the pool: first the management entity of the building. If it does not deal with the complaint within 14 days, it goes to RERA (art. 24).

Complaints against the developer

RERA considers complaints against developers about the management of jointly owned property (art. 33).

Disputes

Disputes over rights and obligations under the law go to the Rental Disputes Settlement Centre, which has exclusive jurisdiction (art. 42).

When to call an inspection after moving in

Before the 1-year period for installations ends. An inspection in the last months documents what is left with measurements, while the developer is still liable for it.

Questions after handover

01

Does the warranty cover the air conditioning?

AC is a mechanical installation, so it falls under the 1-year period from handover under Dubai Law No. 6 of 2019, art. 40.

02

Does the year run from my handover or from the building’s completion?

From the handover of your unit. If the owner does not take possession, it runs from the completion certificate.

03

Who repairs the lobby, the lifts or the pool?

They are common parts: complain to the management entity first; after 14 days without action, to RERA.

04

Do I need an engineer’s report to claim?

No: a written list with a photo and the location of each defect is enough to start. A report with measurements makes items hard to dispute.

05

Are cracks in the walls covered for ten years?

Defects of the structural parts are, for 10 years from the completion certificate. Whether a crack is structural is for an engineer to say; finishes follow your sale agreement.

Your own question?

Write it here. It goes to our snagging team in WhatsApp, and they answer there.

Your own question? Ask in WhatsApp

Book an inspection

Leave a number and the handover date. We will confirm the price and the slot the same day.

Phone or WhatsApp

Get a consultation

We reply on WhatsApp within a working day.